Infrastructure Assessment as a Mechanism to Enhance Spatial and Strategic Planning and Decision Making in Determining Development Priorities Within Urban Areas in Developing Countries
Abstract:
The inherited spatial, land use and transportation form in developing countries represent various challenges in addressing effectiveness and efficiency in attaining resilience and sustainability goals and objectives for urban development. Addressing development and growth in spatial systems within urban areas in developing countries are too often guided and determined by political preferences of decision makers. This practice is applied notwithstanding the existence of planning instruments in developing countries to guide decision making in a technical and accountable preferred practice.
Priorities for development in such countries is thus determined subjectively notwithstanding the variety of needs to be addressed with restricted resources for development capital as well as allocation of funding for maintenance and operational practices related to infrastructure and transportation systems. Socio-economic realities complicate decision making further.
The objective of this paper is to demonstrate the use of modelling tools to guide strategic planning and decision making in determining development priorities in urban areas within developing countries. It will consider components such as spatial and land use planning and development realities; infrastructural input and needs; application of standards and a prioritisation approach towards optimal development and application of best practices.
1. Introduction
Land use and transportation in developing countries are directly related to its founding spatial system development realities that are in many cases dependent on its historical colonial spatial form, linkages and external influences. In this context, the origins of urban spatial structure and transportation systems in many developing countries have been influenced by specific geographical and agricultural development forces and in many cases due to commercial exploitation of its natural and mineral resources. The resulting urban and regional form in many cases focussed on political agendas underlying regional, urban, transportation planning and development. In most cases the impact of environmental and socio-economic forces was not considered in an integrated fashion due to ad hoc decision making by political decision makers. Such decision making were mainly guided by the preferred needs of developers and not by preferences of the electorate and needs of population and communities in developing such spatial systems. With the process of de-colonialism that followed independence in some developing countries, the core planning challenge was spatial transformation through several planning instruments such as spatial development plans; land use management systems; transportation plans; infrastructure development plans underpinned by strategic planning that were introduced in many cases in an ad hoc fashion due to ongoing political agendas.
The need to align, integrate preferred spatial development orientated planning instruments may be enhanced through development of transformative spatial development modelling instruments to promote, guide and integrate planning and decision making in a democratic way that will result in fair and justifiable decision making that will be sustainable and resilient. Articulation of potential, needs and priorities in the case of developing countries needs to be accountable towards future generations. It will assist spatial and transportation planning and development in an endeavour to capacitate decision makers in an accountable fashion by promoting effective and efficient development decision making that is socially, economically and politically accountable towards present and future generations.
2. Spatial and Transportation Modelling
Land use and spatial development is based on accessibility, density, location of workplaces, floor space provision, prices and related location determinants. From the work of Waddell [1] follows that theoretical integrated transportation and land use models are in practice not reliable and easy to use (i.e. also not transparent) due to a lack of staff capacity understanding such models, how it works, how to apply it and why. This statement is even more applicable to developing countries with their huge lack of specialised human capacity. Figs. 1 and 2 provide more information on land-use and transport interaction.
Schoeman [3] assess, integrate and articulate the South African transport interfaces between different spatial strategic instruments and formulates KPIs for application in strategic planning instruments guiding transportation planning in RSA. The author further in [4] links transportation targets identified in South-African’s different strategic instruments to measurable and comparable annual targets applicable to the local municipality sphere of government.
3. Development Focuses and Approaches
In South-Africa the National Development Plan (NDP) [5] identifies a set of national development priorities and targets inclusive of prosperity, equality, economic growth and employment attributes. In development the legal framework is facilitated by the Spatial Planning and Land Use Management Act (SPLUMA) [6] and the supporting policy framework contained in the Integrated Urban Development Framework (IUDF) [7]. The National Spatial Development Framework (NSDF Final Draft) [8] guides and informs decision making for land use planning and development for the national as well as other spheres of government. The NSDF
[8] outlines specific arrangements for prioritising, mobilising, sequencing and implementing public and private infrastructural and land development investment in identifying priority spatial restructuring areas provided for in the framework. National spatial development pri- orities are informed by challenges and trends, objectives and gaps in addressing spatial development, vision, objectives and the spatial status quo. The priorities direct spatial restructuring by identifying developmental interventions in national, regional and local spaces and priorities and preferences for spatial restructuring and development in facilitating accelerated spatial transformation.


The NSDF (2018) thus endeavours to direct, guide and align:
• all infrastructure investment and development spending decisions by national sector departments;
• planning, budgeting and implementation across all spheres and between sectors of government.
The NSDF ([8], p. 177) thus requires the development of a monitoring and evaluation framework which will engage all three spheres of government.
Local development is directed by the specific legislation and policies. For further information on this consider sources of Department of Planning, Monitoring and Evaluation (DPME) [9,10]. Section 26(e) in Local Government Municipal Structure Act (MSA) no. 32 of 2000 [11] state that all municipalities must compile a Spatial Development Framework (SDF) which direct and coordinate development within municipalities and prescribes that each municipality has to formulate an annual strategic municipal development plan (SMDP) to direct decisions, development programmes and budgets. Section 25 in the MSA [11] requires Integrated Development Plans (IDP) for each municipality to be formulated to achieve aligned planning with bordering municipalities (inclusive of Integrated Transport Plans and Performance Management Frameworks), organs of state as well as provincial and national legislation and policies.
The DPME [9] core responsibility is monitoring planning between the plans and programmes and evaluation of planning instruments within the three spheres of government. The DPME [9] states that the weaknesses in planning and development is due to a lack of alignment between plans and budgets; the absence of clarity on the powers and functions of the DPME and absence of prioritisation within government’s plans and actions. The Municipal Finance Management Act (MFMA) no. 53 of 2003 [12] encourages the allocation of resources in line with strategic priorities. Furthermore, it also links plans and budgets in achieving sustainable and financial goals (Section 21 of the Act). The Guidelines for Infrastructure Asset Management in Local Government (2006–2009) [13] suggest annual updated Infrastructure Asset Management Plan (IAMP) for each municipality that must include information on different sectors (such as roads etc.); priorities and needs; levels of service (LOS); future demand; capital works and funding plans. Unfortunately, these annual updated IAMP and SMDP are still not a reality in 2019.
Furthermore, it is noted that cross-sector issues (in support of disadvantaged South Africans) and priorities are considered in the Comprehensive Municipal Infrastructure Plan (CMIP) which presents a complete long-term plan for the municipality’s infrastructure assets (key issues and strategic options). The CMIP fund the provision of new services, the upgrading of a service lower than basic levels to a basic level of service and special (adverse geo- technical, environmental and geo-hydrological) cases.
Municipalities are categorised in the Municipal Infrastructure Investment Framework (MIIF) [14] in the following categories: A = Cities or Metros (6), B1 = Secondary Cities (19) with an average municipality population of 438,540; B2 = Large Towns (26) (average municipality population of 182,786); B3 = Small Towns (101) (average municipality population of 81,701); B4 = Municipalities in rural areas (59) (average municipality population of 205,458), C1 = district municipalities that are not water services providers and generally have few service delivery functions (23), C2 = district municipalities that are water services providers and often have substantial obligations (21). District municipalities have also taken over the responsibility for supplying water and sanitation in certain municipal areas.
Stats SA [15] states that Category A municipalities accommodated 40% of South Africa’s population in 2016 but were responsible for 56% of total expenditure. Category B4 municipalities accommodated 24% of the national population, but invested only 6% of the total municipal budget. Eskom provides electricity directly to 94% rural municipal areas without such municipalities’ contribution to expenditure for electricity infrastructure development, distribution and maintenance in such areas.
Table 1 provides information on the different infrastructure competencies of municipalities as in 2018.
In 2014 the South African municipality’s functionality (in terms of the five basics inclusive of political stability, governance, service delivery, financial & institutional management and community satisfaction) were classified by COGTA [17] into four categories: top performance 7% (performance above average, basics correct and innovative); reasonable performance 30% (basics complies but still have much to do); middle performance 32% (almost dysfunctional and need assistance to get the basics correct ) and the dysfunctional municipalities with bottom performance 31% (performance unacceptable, corruption, negative audits, poor service delivery, no community engagement). Furthermore, it is concluded that dysfunctional municipalities and its continuous negative outcome and lack of service delivery were the product of corruption, councils which did not work, a lack of structured community engagement, poor financial management standards and political management of municipalities.
| B1 | B2 | B3 | B4 | C1 | C2 | Total |
Electricity | 100% | 96% | 92% | 44% | 0% | 40% | 78% |
Housing | 83% | 62% | 47% | 26% | – | – | 47% |
Municipal public transport | 57% | 17% | 19% | 35% | 17% | 40% | 28% |
Municipal roads | 78% | 73% | 63% | 67% | – | – | 67% |
Sanitation | 95% | 71% | 74% | 30% | 0% | 81% | 66% |
Solid waste | 100% | 100% | 96% | 91% | 25% | 25% | 93% |
Storm water management | 67% | 71% | 73% | 87% | – | – | 76% |
Water | 100% | 89% | 89% | 100% | 25% | 95% | 91% |
Department of Public Works [18] states that Category B municipalities do not have asset management plans, maintenance budgets, lack capacity, and their leadership does not regard maintenance to be essential.
Note that the municipality boundaries were amended in 2005, 2011 and 2016 which make it difficult to build up historical data for such municipalities.
The different grants each municipality receives need to be consolidated. There are various development grants for which municipalities may apply for:
• Rural Roads Asset Management Grant;
• Rural Households Infrastructure Grant;
• Intermediate cities: Integrated Urban Development Grant;
• Integrated Cities Development Grant;
• Neighbourhood Development Partnership Grant;
• Integrated National Electrification Programme (municipalities);
• Municipal Water Infrastructure Grant;
• Regional Bulk Infrastructure Grant;
• Public Transport Infrastructure and Systems Grant;
• Urbans Settlements Development Grant;
• Municipal Infrastructure Grant (MIG).
The MIG (introduced in 2004) facilitates budget, planning, operational and financial management of infrastructure investment, development and modernisation. It forms part of the responsibility of the Municipal Manager as pointed out by DPLG (2006) [19]. Underspending in MIG projects leads to inefficient service delivery.
COGTA [20] concludes that this underspending is due to:
• Lack of an independent Project Management Units;
• Time frames that was not met;
• Poorly functioning intergovernmental relations (lack of alignment between national, provincial and municipal priorities);
• Procurement plans not being adhered to;
• Incompetent appointed service providers;
• Lack of community involvement;
• Lack of clear-cut MIG policies (limited legislative to prevent municipalities from changing commitments, especially in the year of implementation);
• High staff turnover rates;
• Lack of monitoring and reporting.
No MIG funds may be spent outside the framework of a municipality’s pre-existing Integrated Development Plan (IDP) and approved budget. The IDP focuses on the provision of basic package services to the poor; appropriate services levels; financial sustainability and the presence of adequate organisational capacity. MIG policies are not always clear, or shielded from political influence and pressure. MIG projects are aimed at households that earn R2,400/month or less and focussing on the poor in communities.
For prioritised projects local municipalities may distribute MIG allocations as follows:
0.54 Sanitation + 0.17 (Roads and storm water) + 0.04 (Refuse removal & street lighting) + 0.15 (community facilities and centres, sport facilities, social services, emergency services, parks, open spaces and public transport) + 0.05 (new and rehabilitation of social institutions) + 0.05 (urban renewal and rural development of nodal municipalities) + (past performance constant).
Figure 3 illustrates a decline in the backlogs. In the last decade the decline in backlogs were 12% for sanitation, 10% for electricity in home, 5% for water in home, 4% for formal dwelling (i.e. structure built according to approved plans with/without running water and/or flush toilet within the dwelling) and for no formal refuse removal (i.e. refuse is not removed by the local authorities) 3%. Table 2 provides a summary of the different backlogs per municipality category in 2009. The minimum LOS recommends residential roads with all-weather access within 500 m of a dwelling (COGTA [21]). Note that Fig. 3 does not contain any data on road infrastructure that is due to the fact that Stats SA does not consider road accessibility as an important infrastructure service, therefore it is also not included in Stats SA’s Service Deliv- ery Index or Infrastructure Quality Index.
Table 2 shows higher than average backlog values. It is deduced that the highest backlog values are in the category B4 and B3 municipalities. Funds will not solve the problems in these Category B4 and B3 municipalities since it is concluded that the cause of these back- logs are due to soft issues like lack of management and staff capacity [18].

4. Determining Development Priorities
Waddell [1] states that models which predict the future dependent on uncertain input variables, therefore policy-makers must know which uncertain inputs were used in the model- ling process that inform their decisions. The IUDF [7] states that one of the key challenges at local sphere of government include the assessment and monitoring of municipal performance. However, currently monitoring is unsuccessful due to inadequate analytical capacity to generate real insight into actual performance and risk management.
In 1996 the UN-Habitat developed the City Development Index [23] which assesses well- being and access to facilities by urban residents in considering the factors of infrastructure, waste, health, education and city product. It includes the following measures:
Infrastructure = 0.25 Water connection; + 0.25 Electricity; + 0.25 Sewerage; + 0.25 Telephone; Waste = 0.5 (Wastewater treated); + 0.5 (Formal solid waste disposal).
Table 3 lists the 20 municipalities in South Africa with the highest backlogs (in terms of number of households) in 2017 for the different categories of infrastructure. It illustrates that Madibeng municipality has a formal housing backlog of 69,907; sanitation backlog is the highest in Bushbuckridge (98,047 households); water infrastructure backlog is the high- est in King Sabata Dalindyebo where 65,848 households are without water connections; the electricity connections backlog in Emalahleni is 45,363 and in City of Mbombela there are 144,389 households without refuse removal services.
|
|
|
| Road length per household per metres | Refuse removal | |||||
Backlog | Water | Sanitation | Electricity | Paved | Paved and gravel | Paved, gravel & earth surfaced roads | Curb side removal | Own refuse dump | Communal dumping site | No rubbish disposal or other |
A | 2% | 11% | 21% | 8.1% | 10% | 10.6% | 89% | 5% | 2% | 3% |
B1 | 4% | 20% | 24% | 5.4% | 16.3% | 23.4% | 69% | 23% | 2% | 5% |
B2 | 10% | 21% | 24% | 6.5% | 44.1% | 50.3% | 63% | 28% | 2% | 7% |
B3 | 4% | 27% | 26% | 4.9% | 29.4% | 33.7% | 56% | 33% | 2% | 8% |
B4 | 25% | 44% | 42% | 7.7% | 57.2% | 65.9% | 12% | 71% | 1% | 16% |
Ave | 9% | 24% | 27% | 7% | 27% | 31.6% | 61% | 29% | 2% | 7% |
Formal housing Backlog Sanitation | Water infrastructure | Electricity connections | Refuse removal | ||||||
Madibeng | 69,907 | Bushbuckridge | 98,047 | King Sabata Dalindyebo | 65,848 | Emalahleni | 45,363 | City of Mbombela (incl Umjindi) | 144,390 |
Rustenburg | 57,910 | Madibeng | 96,507 | Ingquza Hill | 57,784 | Rustenburg | 31,087 | Bushbuckridge | 132,859 |
King Sabata | 52,592 | City of Mbombela | 95,390 | Greater | 54,775 | uMhlabuyalin- | 27,185 | Polokwane | 130,042 |
Dalindyebo |
| (incl Umjindi) |
| Tubatse/ |
| gana |
|
|
|
|
|
|
| Fetakgomo |
|
|
|
|
|
Msunduzi | 50,007 | Polokwane | 92,725 | Thulamela | 51,103 | Jozini | 23,232 | Madibeng | 116,272 |
Nyandeni | 44,163 | Greater Tubatse/ | 82,476 | Nyandeni | 50,156 | Madibeng | 23,111 | Thulamela | 112,016 |
|
| Fetakgomo |
|
|
|
|
|
|
|
Mbhashe | 41,168 | Rustenburg | 66,056 | Mbizana | 48,878 | Matatiele | 22,246 | Greater Tubatse/ | 109,987 |
|
|
|
|
|
|
|
| Fetakgomo |
|
Mnquma | 36,949 | Nkomazi | 60,448 | Greater | 46,693 | Randfontein/ | 19,670 | Greater Tzaneen | 103,275 |
|
|
|
| Tzaneen |
| Westonaria |
|
|
|
Ingquza Hill | 36,323 | Thulamela | 59,573 | Bushbuckridge | 45,286 | Umzimvubu | 19,203 | Makhado | 101,996 |
Emfuleni | 35,581 | Makhuduthamaga | 53,318 | Makhado | 41,029 | Mbhashe | 18,972 | Msunduzi | 98,485 |
Mogale City | 34,650 | Greater Tzaneen | 52,455 | City of | 40,436 | King Sabata | 18,882 | King Sabata | 90,894 |
|
|
|
| Mbombela (incl |
| Dalindyebo |
| Dalindyebo |
|
|
|
|
| Umjindi) |
|
|
|
|
|
Emalahleni | 32,364 | Makhado | 51,407 | Mbhashe | 37,425 | Mogale City | 16,896 | Nkomazi | 86,622 |
uMzimkhulu | 31,834 | Elias Motsoaledi | 47,467 | Collins | 34,593 | Msinga | 16,152 | Thembisile Hani | 80,444 |
|
|
|
| Chabane |
|
|
|
|
|
|
|
|
| (Mutale) |
|
|
|
|
|
Intsika Yethu | 31,291 | Collins Chabane | 45,425 | Umzimvubu | 33,096 | Mnquma | 15,223 | Collins Chabane | 80,247 |
|
| (Mutale) |
|
|
|
|
| (Mutale) |
|
Engcobo | 29,415 | Moses Kotane | 45,082 | Ray Nkonyeni (Hibiscus Coast & Ezingoleni) | 32,288 | Emfuleni | 15,042 | Maluti-a-Phofung | 77,397 |
Mbizana | 28,910 | Thembisile Hani | 44,506 | Mhlontlo | 31,117 | Polokwane | 14,856 | Nyandeni | 67,470 |
Elundini | 28,842 | Maluti-a-Phofung | 40,219 | Port St Johns | 28,779 | Ntabankulu | 14,456 | Makhuduthamaga | 66,706 |
Mhlontlo | 28,607 | Mogalakwena | 39,955 | uMzimkhulu | 28,458 | Greater Tubatse/ Fetakgomo | 14,081 | Ray Nkonyeni (Hibiscus Coast & Ezingoleni) | 63,822 |
Matatiele | 28,371 | Mahikeng | 36,903 | Mnquma | 28,349 | Mbizana | 12,754 | Greater Giyani | 62,570 |
Umzimvubu | 27,655 | Lepele-Nkumpi | 33,981 | Matatiele | 28,215 | Elundini | 11,618 | Ingquza Hill | 60,239 |
Msinga | 26,817 | Emalahleni | 32,260 | Nongoma | 26,138 | City of Mbombela (incl Umjindi) | 11,501 | Mbhashe | 59,065 |
Stats SA [24] identifies 17 Sustainable Development Goals (SDGs) of which only three are applicable to infrastructure development:
Goal 6: Ensure availability and sustainable management of water and sanitation for all;
Goal 7: Ensure access to affordable, reliable, sustainable and modern energy for all;
Goal 11: Make cities and human settlements inclusive, safe, resilient and sustainable.
It also identifies the following national 2016 baseline percentages:
• Population using safely managed drinking water services 90.2%,
• Wastewater safely treated 52%,
• Population with access to electricity 94.2%,
• Urban population living in informal dwellings 12%,
• Urban residents having access to basic services within informal dwellings:
• Electricity (79.8%), Refuse removal (64.8%), Sanitation (63.9%), Water (96.1%).
From the above data is concluded that formal housing, wastewater treated, refuse removal and sanitation services need argent attention in South Africa. Hence, the suggested national performance weights for informal neighbourhoods due to backlog percentages are as follows:
0.1232 (Informal dwellings) + 0.1047 (Electricity) + 0.3614 (Refuse removal) + 0.3706 (Sanitation) + 0.0401 (Water).
Hence, the National Development Priority list for South African municipalities with the largest service backlog priority in informal neighbourhoods was calculated by considering the weights as calculated in Section 4.2 in combination with the data in Table 3:
1. King Sabata Dalindyebo, 2. Greater Tubatse, 3. Bushbuckridge, 4. City of Mbombela, 5. Thulamela, 6. Mbhashe, 7. Ingquza Hill, 8. Greater Tzaneen, 9. Nyandeni, 10. Mbi- zana, 11. Rustenburg, 12. Makhado, 13. Umzimvubu, 14. Matatiele, 15. Emalahleni.
The development grants as discussed in Section 3.2.3 must be used in support of these municipalities.
The IUDF [7] prioritises the 97 largest urban population municipalities and metros into nine classes. Here, the priorities were determined by considering the urban population statistics of 2011 and the urban growth rate between 2001 and 2011. Thus, Class 1 refers to the highest priority metros (need immediate intervention due to high urban population and urban growth) and Class 9 refers to the lowest priority municipalities (low urban population and low urban growth) but on the short-term priority list (refer to Table 4, Column 3 and 7 for the different priority classes). These classes were used to determine the urban growth priority (Column 2 and 6 in Table 4) which represents an important role to prioritise the budget ratio for infrastructure and resources of different municipalities in the same category class. The urban population and growth priority of 1 refer to the class of metros with the highest urban population and highest urban growth and the priority of 0.2 refer to the class of municipalities with the lowest urban population and lowest urban growth.
The author in [4] applies the short-term priority list as identified in the IUDF [7] as input to determine the urban density priority for each municipality. The high urban density area refers to the urban area with a density greater or equal to 500 persons/km². The density priority is determined by considering the deviation between the relative density and the true density in [4]. In developing countries, the largest proportion of the households is poor there- fore travelling cost is the most important accessibility variable. Population growth, higher car ownership and land cost lead to sprawling development. Burchell et al. [25] note that sprawling development refers to development of relative low density, one that may be too costly to maintain. To support public transport services O’Sullivan [26] provides guidelines for minimum density thresholds. Hence, it is important to determine the urban density priority. The density priority also fulfils an import role in the determination of the public transport priority of municipalities in each class (Column 1 & 5 in Table 4). Here factor 1 refer to an extremely good urban sprawl control results and 0.1 refer to an extremely bad urban sprawl control results.
Primary considerations in the determination of development priorities in urban areas
• The status quo functionality of the municipality (consider [17] for classification). The management and finances of the dysfunctional municipalities (which is almost all B3 and B4 municipalities) need to be sourced out from such municipalities.
• Urban Density priority (Table 4, Columns 1 and 5).
• Urban growth priority (Table 4, Columns 2 and 6). Growth projections are a function of population growth and migration patterns (urbanisation and de-ruralisation). Note that not
all municipalities face growth challenges. The greatest growth is in the metros and secondary municipalities.
• Service backlog priority.
• Budgetary and financial requirements and sources.
• Rehabilitation of ageing infrastructure that needs to be renewed (data on this issue need to be collected).
• Application of correct and applicable level of services.
Secondary core issues in the determination of development priorities in urban areas:
• The risk of delayed in infrastructure implementation\renewals\upgrades\maintenance;
• Community needs and preferences.
Density priority | Urban population and growth priority | Class | Municipality (M) | Density priority | Urban population and growth priority | Class | Municipality (M) |
0.5 | 1 | 1 | City of Tshwane Metro | 0.5 | 0.4 | 7 | Thaba Chweu LM |
0.5 | 1 | 1 | Johannesburg Metro | 0.5 | 0.4 | 7 | uMngeni LM |
0.5 | 1 | 1 | Ekurhuleni Metro | 0.3 | 0.4 | 7 | Kouga LM |
0.3 | 1 | 1 | City of Cape Town Metro | 0.3 | 0.4 | 7 | Khara Hais LM |
0.7 | 0.9 | 2 | eThekwini Metro | 0.3 | 0.4 | 7 | Overstrand LM |
0.5 | 0.9 | 2 | Msunduzi LM | 0.3 | 0.4 | 7 | Swartland LM |
0.1 | 0.9 | 2 | Nelson Mandela Metro | 0.3 | 0.4 | 7 | Umtshezi LM |
0.1 | 0.9 | 2 | Mangaung Metro | 0.3 | 0.4 | 7 | Lesedi LM |
0.7 | 0.8 | 3 | Buffalo City Metro | 0.3 | 0.4 | 7 | Mossel Bay LM |
0.1 | 0.8 | 3 | Emfuleni LM | 0.3 | 0.4 | 7 | Witzenberg LM |
0.8 | 0.7 | 4 | Polokwane LM | 0.3 | 0.4 | 7 | Bela-Bela LM |
0.5 | 0.7 | 4 | Mbombela LM | 0.3 | 0.4 | 7 | Thabazimbi LM |
0.5 | 0.7 | 4 | Rustenburg LM | 0.3 | 0.4 | 7 | Knysna LM |
0.5 | 0.7 | 4 | Madibeng LM | 0.3 | 0.4 | 7 | Victor Khanye |
|
|
|
|
|
|
| LM |
0.5 | 0.7 | 4 | Emalahleni LM | 0.3 | 0.4 | 7 | Mamusa LM |
0.5 | 0.7 | 4 | Thembisile LM | 0.3 | 0.4 | 7 | Umjindi LM |
0.5 | 0.7 | 4 | Mogale City LM | 0.3 | 0.4 | 7 | LekwaTeemane LM |
0.3 | 0.7 | 4 | Kwadukuza LM | 0.3 | 0.4 | 7 | Endumeni LM |
0.3 | 0.7 | 4 | Govan Mbeki LM | 0.9 | 0.3 | 8 | Hibiscus Coast LM |
0.3 | 0.7 | 4 | Steve Tshwete LM | 0.9 | 0.3 | 8 | Elias Motsoaledi LM |
0.3 | 0.7 | 4 | Sol Plaatjie LM | 0.9 | 0.3 | 8 | Makeng LM |
0.3 | 0.7 | 4 | Metsimaholo LM | 0.9 | 0.3 | 8 | Abaqulusi LM |
0.1 | 0.7 | 4 | Drakenstein LM | 0.9 | 0.3 | 8 | BaPhalaborwa LM |
0.1 | 0.7 | 4 | George LM | 0.9 | 0.3 | 8 | Ditsobotla LM |
0.1 | 0.7 | 4 | Tlokwe LM | 0.7 | 0.3 | 8 | Lekwa LM |
0.1 | 0.7 | 4 | Stellenbosh LM | 0.7 | 0.3 | 8 | Oudtshoorn LM |
0.7 | 0.6 | 5 | uMhlathuze LM | 0.5 | 0.3 | 8 | Theewaterskloof LM |
0.7 | 0.6 | 5 | Matlosana LM | 0.5 | 0.3 | 8 | Ndlambe LM |
0.1 | 0.6 | 5 | Msukalingwa LM | 0.3 | 0.3 | 8 | Naledi LM Maquassi |
0.1 | 0.6 | 5 | Randfontein LM | 0.3 | 0.3 | 8 | Hills LM |
0.1 | 0.6 | 5 | Breede Valley LM | 0.3 | 0.3 | 8 | Greater Kokstad LM |
0.9 | 0.5 | 6 | Thulamela LM | 0.3 | 0.3 | 8 | Langeberg LM |
0.7 | 0.5 | 6 | Mogalakwena LM | 0.9 | 0.2 | 9 | Bushbuckridge LM |
0.7 | 0.5 | 6 | King Sabata Dalindyebo | 0.9 | 0.2 | 9 | Greater Tzaneen LM |
0.7 | 0.5 | 6 | Maluti-A-Phofung LM | 0.9 | 0.2 | 9 | Dr JS Moroka LM |
0.7 | 0.5 | 6 | Matjhabeng LM | 0.9 | 0.2 | 9 | Albert Luthuli LM |
0.7 | 0.5 | 6 | Newcastle LM | 0.9 | 0.2 | 9 | Nkokobe LM |
0.7 | 0.5 | 6 | Lukhanji LM | 0.9 | 0.2 | 9 | Mnquma LM |
0.7 | 0.5 | 6 | Emnambithi LM | 0.7 | 0.2 | 9 | Tswaing LM |
0.7 | 0.5 | 6 | Merafong LM | 0.7 | 0.2 | 9 | Pixley Ka Seme LM |
0.1 | 0.5 | 6 | Ngwathe LM | 0.7 | 0.2 | 9 | Mafube LM |
0.1 | 0.5 | 6 | Moqhaka LM | 0.5 | 0.2 | 9 | Phokwane LM |
0.1 | 0.5 | 6 | Westonaria LM | 0.5 | 0.2 | 9 | Nala LM |
0.1 | 0.5 | 6 | Dihlabeng LM | 0.5 | 0.2 | 9 | Makana LM |
0.1 | 0.5 | 6 | Setsoto LM | 0.5 | 0.2 | 9 | Masilonyana LM |
0.5 | 0.4 | 7 | Lephalale LM | 0.5 | 0.2 | 9 | Inxuba Yethemba LM |
0.5 | 0.4 | 7 | Saldhana Bay LM | 0.5 | 0.2 | 9 | Nketoana LM |
0.5 | 0.4 | 7 | Mkhondo LM | 0.5 | 0.2 | 9 | Modimolle LM |
0.5 | 0.4 | 7 | Midvaal LM |
|
|
|
|
5. Conclusions
The infrastructure function, practices and level of services municipalities must apply and adhere to differ. Currently, the municipalities boundaries changes more or less every 5 years due to political preference; access and data on road infrastructure is consider as unimportant; there is a lack of evaluation and assessment criteria for municipalities within the same class. As a developing country, South Africa finds itself in a planning spiral formulating different plans without integration, articulation and consideration of existing plans and regulations. For efficient management and decision making within all municipalities there must be an annually updated Infrastructure Asset Management Plan (which include roads and transport), Strategic Municipal Development Plan supported by an approved Implementation, Maintenance and Budget Framework.
The data used to support the findings of this study are available from the corresponding author upon request.
The author gratefully acknowledges the National Research Foundation (GUN No. 81221) for financial support. Any opinion, finding and conclusion or recommendation expressed in this material is that of the author and the NRF does not accept any liability in this regard.
The authors declare that they have no conflicts of interest.